Materials Handling Contractor Planning Tool

Contractor Planning Tool

Improve Productivity & Meet Schedules

Productivity drops and schedules get delayed when workers have to wait for materials to be delivered or spend time and energy locating and manually lifting and carrying materials around a jobsite. Industry stakeholders estimate that:

  • The average daily waiting time by trade ranges from about 45 minutes to 83 minutes.(1)
  • 鈥淓very 1 minute spent on pre-planning saves 6 minutes in the field.鈥 (2)

 

Planning to reduce manual materials handling is a key part of Lean Construction and other approaches used to improve construction performance. Productivity can be improved when plans incorporate the following:

  • Lifting equipment 鈥撎The Ohio Bureau of Workers鈥 Compensation found a reduction in days lost due to soft tissue injuries听(back injuries, etc.) when contractors used selected lift assist equipment.听(3)
  • Lift teams 鈥撎Researchers found that two-mason lift teams reduced the risk for injury and reduced by 37% the average amount of time to build a wall.听(4)Mason contractors that use two-mason lift teams cite benefits including safety听(less wear and tear on workers, less low back stress, and less fatigue)听and increased productivity.(5)
  • Lower-weight materials 鈥撎An industry study of light-weight block produced an average increase in production of 14.7%.(6)
  • Prevention through Design (PtD)听鈥撎Contractor and employee developed solutions, for example building a slide from plywood or lumber to move a material to a lower level where it will be used, can reduce manual materials handling.
  • Storage 鈥撎Construction materials delivered on pre-loaded and stackable carts reduce the risks of multiple unnecessary handling of material, and of potential soft tissue injuries.(7)